It has been applied using cranes or insertion methods to install heavy structures to strengthen existing railway bridges. These methods are uneconomical because of two reasons. The first one is it is required to construct approach roads for heavy equipment and/or working yard. The second one is the electric lines shall be cutoff during construction. Both require additional construction cost and duration. In this study, new transport equipment was developed which can be applied to heavy structures up to 100 ton. Using this method, the heavy structure can be loaded into the new transport equipment at working yard and transported to the working site. This method can be applied, but not limited to railway bridge or roadbed rehabilitation. It was found that the precious construction can be achieved to install heavy structure using this method. The experimental construction to make non-ballast girder bridge composite with new pc deck slab using this method was carried out for Jewon bridge. The example bridge is in extreme condition because it locates above national road #38 within extreme transition curve and has 10 ‰ slope and skew. The experimental construction results were satisfactory both for safety and construction precision.
- 제목
- 선로 이송 가설공법을 적용한 철도판형교 유도상화
- 제목 (타언어)
- An experimental construction of railway steel plate girder strengthen adding ballast system by transport equipment
- 저자
- 민지홍; 서종원; 장형식; 박준원
- 발행일
- 2011-05
- 유형
- Proceeding
- 저널명
- 한국철도학회 2011년도 춘계학술대회 논문집
- 페이지
- 707 ~ 716